Lawsuit may muck up downtown plan

Just when you thought Amarillo was set to take a major step toward downtown revival, something gets in the way … maybe.

The Amarillo Economic Development Corporation announced plans to file a lawsuit to recover $1.6 million from the company that built the CenterPort Business Park in east Amarillo. Yes, it’s some distance from downtown.

But hold on.

The CenterPort site is now vacant. Another business lured here by AEDC gave up on its wind-turbine construction project and left. The city wants to relocate the Coca-Cola distribution center, which is currently downtown, to the CenterPort site. Except that it’s structurally unsound. The foundation is a mess, according to AEDC. It needs to rebuilt.

The firm that built the place, Commercial Industrial Builders, muffed the job. AEDC wants the company to pay back the money that AEDC says it will have to spend to fix the site.

What does this mean for downtown’s revival? Well, the Coca-Cola site is supposed to become home to a multipurpose entertainment venue to be built, along with a downtown hotel and a huge parking garage. The legal action just might gum up those works if CIB fights hard to keep from paying the money AEDC wants.

AEDC President and CEO Buzz David said the agency sought to resolve the dispute without going to court. The efforts so far have failed. Perhaps the threat of a lawsuit might spur CIB to pony up the cash so that AEDC can fix what it says is wrong with the building.

If the threat doesn’t work, I’m afraid we’re in for a lengthy delay on downtown’s move forward.